Last Turbine Goes Up At Nine Canyon, Usa: RES Completes Construction For Energy Northwest

Renewable Energy Systems (USA) is celebrating the erection of the final turbine of the 48MW Nine Canyon Wind Project, in the state of Washington, USA. The wind farm, the largest public-owned wind project in the USA, has been built on a turnkey contract by RES (USA) for Energy Northwest and will be handed over this week.

Construction of the 37 Bonus turbines, each with a capacity of 1.3MW, has taken just three months and the project was completed on schedule, despite numerous days when wind conditions were so fierce that work had to be stopped. Turbine delivery was an outstanding success, with barges being used to transport turbines and towers along the Columbia River.

Chris Morgan, Engineering Director for the RES Group, said;

"This has been a tremendously successful construction project for RES on behalf of our valued client Energy Northwest. RES, turbine supplier Bonus, and all other parties involved have worked together to overcome the challenges it has presented, in order to meet the project deadline. This is RES’ first project for Energy Northwest and our first in this part of the US. We have enjoyed the collaboration and we look forward to extending our operations in this region."

Dan Porter, Energy Northwest’s manager of project development commented;

"I want to congratulate RES on achieving this terrific milestone. Chris Hills and the entire RES organization are producing an outstanding project and we at Energy Northwest could not have been more pleased with their commitment and performance.".

Project milestones have included:

November 2001: RES awarded contract by Energy Northwest for construction of project

14 January 2002: work starts on roads
11 March: commencement of foundation construction

23 May: turbine erection commences

3 July: first turbine commissioned and handed over to Energy Northwest
19 August: final turbine erection completed
26 August: turbine commissioning completed and project handed over to Energy Northwest

Energy Northwest will own the Nine Canyon Wind Project and will be responsible for operation and maintenance. The power from the project will be bought by nine different utilities in the state of Washington: Benton PUD (Public Utility District), Chelan PUD, Douglas PUD, Grant PUD, Grays Harbor PUD, Lewis PUD, Mason PUD, Okanogan PUD and Columbia Generating Station.

ENDS

Notes to Editors
1.

RES (USA) Inc is a member of the Renewable Energy Systems (RES) group of companies, which is part of the UK’s Sir Robert McAlpine group. RES is one of the world’s leading wind developers, with offices in 9 countries and over 6000MW of wind power capacity on its books at various stages of development. In 2001, RES completed construction of the world’s largest wind farm at King Mountain, Texas (280MW) and has to date built over 540MW of wind power capacity in the USA.

2.Energy Northwest owns and operates the 1,200MW Columbia Generating Station near Richland, Washington, the White Bluffs Solar Station, and the 27MW Packwood Lake Hydroelectric Project.
3.The wind project is located in the south of the state of Washington, about two miles east of Jump Off Joe Butte and about eight miles southeast of Kennewick.
4.A photo of the final turbine going up accompanies this release. Further photos of construction of the Nine Canyon wind farm are available by email. Contact anna.stanford@res-ltd.com
CONTACT:

Anna Stanford, Media Officer, RES Ltd +44 (0)1795 536667 (w) or +44 (0)776 110 3465 (m)