» Cameron Ridge
» Pacific Crest
» Llano Estacado
» Woodward Mountain
» King Mountain
» Nine Canyon I
» Nine Canyon II
» Wigton
» Sweetwater II
» Ainsworth
» Hopkins Ridge
» Wild Horse
» Sweetwater 1V(b)
» Marengo I
» White Creek
» Sweetwater V
» Whirlwind
» Nine Canyon III
» Mountain Wind I
» Lone Star
» Pacific Crest
» Llano Estacado
» Woodward Mountain
» King Mountain
» Nine Canyon I
» Nine Canyon II
» Wigton
» Sweetwater II
» Ainsworth
» Hopkins Ridge
» Wild Horse
» Sweetwater 1V(b)
» Marengo I
» White Creek
» Sweetwater V
» Whirlwind
» Nine Canyon III
» Mountain Wind I
» Lone Star

King Mountain Wind Ranch
Upton County, Texas
This site is located on a mesa in Upton County, West Texas, some 20 miles from the Woodward Mountain Project.
RES co-developed this project which had the following power purchase agreements:
- 198.9MW with Reliant Energy,
- 76.7MW with Austin Energy and
- 2.6MW with TNMP.
The 214 wind turbines connect to the grid network via four 85MVA primary substations.
RES acted as the Engineering, Procurement & Construction (EPC) contractor and completed the wind ranch in December 2001.

Information on the Project
| RES's Role: | Developer and EPC construction contractor |
| Developer: | RES and Cielo |
| Owner: | FPL |
| Installed Capacity: | 278 MW |
| Number of Turbines: | 214 |
| Turbine Rating: | 1300 kW |
| Turbine Type: | Bonus, Active Stall |
| Year of Operation: | 2001 |